# Channel Downcutting and Widening

&#x20;             While sediment transport calculations have traditionally been made with the same channel dimensions throughout a simulation, SWAT+ will model channel downcutting and widening. When channel downcutting and widening is simulated, channel dimensions are allowed to change during the simulation period.

&#x20;             Three channel dimensions are allowed to vary in channel downcutting and widening simulations: bankfull depth, $$depth\_{bnkfull}$$, channel width, $$W\_{bnkfull}$$, and channel slope, $$slp\_{ch}$$. Channel dimensions are updated using the following equations when the volume of water in the reach exceeds 1.4 × 106 m$$^3$$.

&#x20;              The amount of downcutting is calculated (Allen et al., 1999):

&#x20;                       $$depth\_{dcut}=358.6*depth*slp\_{ch}\*K\_{CH}$$                                           7:2.5.1

&#x20;             where $$depth\_{dcut}$$ is the amount of downcutting (m), $$depth$$ is the depth of water in channel (m), $$slp\_{ch}$$ is the channel slope (m/m), and $$K\_{CH}$$ is the channel erodibility coefficient (cm/h/Pa).

&#x20;               The new bankfull depth is calculated:

&#x20;                     $$depth\_{bnkfull}=depth\_{bnkfull,i}+depth\_{dcut}$$                                            7:2.5.2

where $$depth\_{bnkfull}$$ is the new bankfull depth (m), $$depth\_{bnkfull,i}$$ is the previous bankfull depth, and $$depth\_{dcut}$$ is the amount of downcutting (m).

&#x20;                The new bank width is calculated:

&#x20;                         $$W\_{bnkfull}=ratio\_{WD}\*depth\_{bnkfull}$$                                                   7:2.5.3

where $$W\_{bnkfull}$$ is the new width of the channel at the top of the bank (m), $$ratio\_{WD}$$ is the channel width to depth ratio, and $$depth\_{bnkfull}$$ is the new bankfull depth (m).

&#x20;                 The new channel slope is calculated:

&#x20;                             $$slp\_{ch}=slp\_{ch,i}-\frac{depth\_{dcut}}{1000\*L\_{ch}}$$                                                               7:2.5.4

where $$slp\_{ch}$$ is the new channel slope (m/m), $$slp\_{ch,i}$$ is the previous channel slope (m/m), $$depth\_{bnkfull}$$ is the new bankfull depth (m), and $$L\_{ch}$$ is the channel length (km).

Table 7:2-2: SWAT+ input variables that pertain to channel downcutting and widening.

![](https://1348478613-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F-MTFpIHUB1K63DLhLJaf%2Fuploads%2FYguentpOWpC6PwtQpM3U%2Fq3.jpg?alt=media\&token=51095390-2b77-47e5-b5ab-6bbf9de0d0d2)